Noida RERA Report: November 2026

Every project registered with UP-RERA in Gautam Buddh Nagar, from the regulator's public records, updated 4 November 2026. The numbers on this page refresh every night.

WhatsApp
1,126
projects registered
51%
housing projects with extended deadlines
30,578
buyer complaints on UP-RERA
170
projects on the NCLT list

Key findings

  • 1,126 real estate projects are registered with UP-RERA in Gautam Buddh Nagar (Noida, Greater Noida, Greater Noida West and the Yamuna Expressway), with 3,19,375+ flats in the projects that report their size.
  • 51% of housing projects (443 of 873) have had their RERA completion deadline extended at least once — on average by 20 months. 112 were extended by two years or more.
  • Buyers have filed 30,578 complaints against these projects on UP-RERA — about 5.6 complaints for every 100 registered flats.
  • 170 projects appear on UP-RERA's NCLT list (insolvency proceedings against the builder company); 63 are on the de-registered / defaulter list, 17 had their registration withdrawn and 75 are in abeyance.

By area

Area comes from the project's society page or its pin on UP-RERA's map (nearest sector within 4 km). Projects without a usable location are listed separately.

AreaProjectsFlats*Deadline extendedComplaints / 100 flatsNCLT list
Noida25870,02445%4.125
Greater Noida10525,63942%3.85
Greater Noida West2241,07,64454%5.840
Yamuna Expressway10629,52948%5.532
Location not available43386,53954%768

* Flats in the 550 projects whose size is published on UP-RERA.

How far deadlines moved

Housing projects by total extension of the RERA completion date.

No extension430
Up to 1 year286
1–2 years47
2–3 years42
More than 3 years68

Registrations by year

Projects by the year they were registered with UP-RERA (RERA began in 2017).

The full lists

How we count

  • Source: UP-RERA's public project register, project pages and its NCLT, defaulter, withdrawn and abeyance lists for Gautam Buddh Nagar, read every night.
  • “Extended” compares the completion date the builder first declared with the latest date after all extensions UP-RERA granted. An extension is not a penalty, and many of these projects are complete.
  • Complaints are those filed by buyers against each project, as counted on UP-RERA — not how they were decided. Per 100 flats uses only projects where both numbers are published.
  • Housing excludes projects UP-RERA marks as commercial. Projects registered before RERA (2017) and completed earlier are not in the register.

Use this data

Free to quote and republish with a link to this page (CC BY 4.0). Please cite as:

Source: HomesNCR analysis of UP-RERA data (November 2026) — https://homesncr.in/reports/noida-rera