Rhythm County (Phase Rc-3)
Futureworld Greenhomes Pvt Ltd.
46
Project Health Score
Rhythm County (Phase Rc-3)
High risk · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ737115/15
- Delivery vs promise UP-RERAPromised Dec 2019 · 5 extensions to Jul 2026 · deadline passed 2 months ago with no completion (OC) recorded yet0/20
- Buyer complaints on UP-RERA UP-RERA4 complaints against this project · 255 against the builder8/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ7371
- Registered on
- 2 Aug 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- FUTUREWORLD GREENHOMES PVT. LTD.
- Completion promised
- 31 Dec 2019
- Current deadline
- 31 Jul 2026
- Complaints on UP-RERA
- 4 · builder total 255
Deadline extensions granted (5)
- 1. 31 Dec 2019 → 9 Jun 2020
- 2. 9 Jun 2020 → 8 Dec 2020 · Six months extension in view of force majeure caused by covid-19 pandemic
- 3. 8 Dec 2020 → 31 Mar 2022
- 4. 8 Dec 2020 → 31 Mar 2022
- 5. 31 Mar 2022 → 31 Jul 2026
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in