HOMESNCR

Rhythm County(Phase Rc-1)

Futureworld Greenhomes Pvt Ltd.

30
Project Health Score
Rhythm County(Phase Rc-1)
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ7321
    15/15
  • Delivery vs promise UP-RERA
    Promised Dec 2018 · 6 extensions to Jul 2026 · deadline passed 2 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    63 complaints against this project · 255 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ7321
Registered on
2 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
FUTUREWORLD GREENHOMES PVT. LTD.
Completion promised
31 Dec 2018
Current deadline
31 Jul 2026
Complaints on UP-RERA
63 · builder total 255
Deadline extensions granted (6)
  1. 1. 31 Dec 2018 → 31 Dec 2019
  2. 2. 31 Dec 2019 → 30 May 2020
  3. 3. 30 May 2020 → 29 Nov 2020 · Six months extension in view of force majeure caused by covid-19 pandemic
  4. 4. 29 Nov 2020 → 31 Mar 2021
  5. 5. 31 Mar 2021 → 31 Jul 2025
  6. 6. 31 Jul 2025 → 31 Jul 2026

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in

Loading map…

No flats listed in Rhythm County(Phase Rc-1) right now.

Own a flat here? List it free — buyers searching this society will see it first.

Post your flat