- RERA registration UP-RERAOn UP-RERA's NCLT list: the builder company is in insolvency proceedings for this project0/15
- Delivery vs promise UP-RERAPromised Jun 2018 · 2 extensions to Feb 2023 · deadline passed 43 months ago with no completion (OC) recorded yet0/20
- Buyer complaints on UP-RERA UP-RERA32 complaints against this project · 1347 against the builder0/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ4695
- Registered on
- 29 Jul 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- ADANI INFRASTRUCTURE INTEGRATED SOLUTIONS LIMITED (FORMERLY KNOWN AS JAIPRAKASH ASSOCIATES LIMITED)
- Completion promised
- 30 Jun 2018
- Current deadline
- 28 Feb 2023
- Complaints on UP-RERA
- 32 · builder total 1347
- 1. 30 Jun 2018 → 30 Jan 2022
- 2. 30 Jan 2022 → 28 Feb 2023
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in
Builder or buyer? Something here out of date or wrong — request a correction
We show UP-RERA's public records as they are. If UP-RERA has since updated them (for example, an order was set aside or an extension granted), tell us and share the document — we re-check with UP-RERA and update this page, usually within 2 working days.
No flats listed in Jaypee Greens Kalypso Court (Phase II), Noida right now.
Own a flat here? List it free — buyers searching this society will see it first.
Post your flat