38
Project Health Score
Future Estate (Phase-Fe-3)
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ7386
    15/15
  • Delivery vs promise UP-RERA
    Promised Dec 2019 · 4 extensions to Jul 2026 · deadline passed 2 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    23 complaints against this project · 255 against the builder
    4/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ7386
Registered on
14 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
FUTUREWORLD GREENHOMES PVT. LTD.
Completion promised
31 Dec 2019
Current deadline
31 Jul 2026
Complaints on UP-RERA
23 · builder total 255
Deadline extensions granted (4)
  1. 1. 31 Dec 2019 → 9 Jun 2020
  2. 2. 9 Jun 2020 → 8 Dec 2020 · Six months extension in view of force majeure caused by covid-19 pandemic
  3. 3. 8 Dec 2020 → 31 Mar 2022
  4. 4. 31 Mar 2022 → 31 Jul 2026

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in