Victoryone Amara
Rudra Buildwell Infra Pvt Ltd.
30
Project Health Score
Victoryone Amara
High risk · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ618715/15
- Delivery vs promise UP-RERAPromised Dec 2022 · 3 extensions to Aug 20280/20
- Buyer complaints on UP-RERA UP-RERA63 complaints against this project · 82 against the builder0/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ6187
- Registered on
- 2 Aug 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- RUDRA BUILDWELL INFRA PVT. LTD.
- Completion promised
- 31 Dec 2022
- Current deadline
- 23 Aug 2028
- Complaints on UP-RERA
- 63 · builder total 82
Deadline extensions granted (3)
- 1. 31 Dec 2022 → 30 Jun 2023 · Six months extension in view of force majeure caused by covid-19 pandemic
- 2. 30 Jun 2023 → 29 Mar 2025
- 3. 29 Mar 2025 → 23 Aug 2028
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in