The Hemisphere_Phase-1
Royalgolf Link City Projects Pvt Ltd
30
Project Health Score
The Hemisphere_Phase-1
High risk · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ423215/15
- Delivery vs promise UP-RERAPromised Dec 2022 · 1 extension to Jun 2023 · deadline passed 40 months ago with no completion (OC) recorded yet0/20
- Buyer complaints on UP-RERA UP-RERA148 complaints against this project · 371 against the builder0/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ4232
- Registered on
- 1 Aug 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- ROYALGOLF LINK CITY PROJECTS PRIVATE LIMITED
- Completion promised
- 9 Dec 2022
- Current deadline
- 8 Jun 2023
- Complaints on UP-RERA
- 148 · builder total 371
Deadline extensions granted (1)
- 1. 9 Dec 2022 → 8 Jun 2023 · Six months extension in view of force majeure caused by covid-19 pandemic
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in