Shivalik Homes 2

Cosmos Infraestate Pvt Ltd. Eelevates Infratech Private Limited

30
Project Health Score
Shivalik Homes 2
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ5819
    15/15
  • Delivery vs promise UP-RERA
    Promised Mar 2021 · 2 extensions to Dec 2028
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    198 complaints against this project · 213 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ5819
Registered on
31 Jul 2017
Type
Residential · New
Promoter (builder company)
COSMOS INFRAESTATE PVT. LTD. EELEVATES INFRATECH PRIVATE LIMITED
Completion promised
31 Mar 2021
Current deadline
31 Dec 2028
Complaints on UP-RERA
198 · builder total 213
Deadline extensions granted (2)
  1. 1. 31 Mar 2021 → 30 Sept 2021 · Six months extension in view of force majeure caused by covid-19 pandemic
  2. 2. 30 Sept 2021 → 31 Dec 2028

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in