Parsvnath Privilege Phase-II

Parsvnath Developers Limited

This project is on UP-RERA's NCLT list: the builder company is in insolvency proceedings. An insolvency professional (IRP) handles the company's affairs. Buying, resale and possession can be delayed; take legal advice before paying. Read the NCLT order.
0
Project Health Score
Parsvnath Privilege Phase-II
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    On UP-RERA's NCLT list: the builder company is in insolvency proceedings for this project
    0/15
  • Delivery vs promise UP-RERA
    Promised Jul 2019 · 0 extensions to Jul 2019 · deadline passed 86 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    44 complaints against this project · 414 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ6067
Registered on
1 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
PARSVNATH DEVELOPERS LIMITED
Completion promised
31 Jul 2019
Current deadline
31 Jul 2019
Complaints on UP-RERA
44 · builder total 414

UP-RERA flag: Default on QPR — the builder has not filed its mandatory quarterly progress report.

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in