Oasis Grandstand Phase-2
Oasis Realtech Pvt Ltd · Sector 22D, Yamuna Expressway
80
Project Health Score
Oasis Grandstand Phase-2
Healthy · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ585804 · flagged “Default on QPR”8/15
- Delivery vs promise UP-RERAWithin schedule · completion due Jan 202920/20
- Buyer complaints on UP-RERA UP-RERA1 complaint against this project · 136 against the builder12/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ585804/01/2025
- Registered on
- 25 Jan 2025
- Type
- Residential · New
- Promoter (builder company)
- OASIS REALTECH PVT LTD
- Completion promised
- 23 Jan 2029
- Current deadline
- 23 Jan 2029
- Complaints on UP-RERA
- 1 · builder total 136
UP-RERA flag: Default on QPR — the builder has not filed its mandatory quarterly progress report.
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in
Loading map…
No flats listed in Oasis Grandstand Phase-2 right now.
Own a flat here? List it free — buyers searching this society will see it first.