Oasis Grandstand ( Phase 1)

Oasis Realtech Pvt Ltd

16
Project Health Score
Oasis Grandstand ( Phase 1)
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ6908 · flagged “Default on QPR”
    8/15
  • Delivery vs promise UP-RERA
    Promised Dec 2019 · 4 extensions to Mar 2023 · deadline passed 42 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    128 complaints against this project · 136 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ6908
Registered on
12 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
OASIS REALTECH PVT LTD
Completion promised
31 Dec 2019
Current deadline
30 Mar 2023
Complaints on UP-RERA
128 · builder total 136

UP-RERA flag: Default on QPR — the builder has not filed its mandatory quarterly progress report.

Deadline extensions granted (4)
  1. 1. 31 Dec 2019 → 30 Dec 2020
  2. 2. 30 Dec 2020 → 29 Jun 2021 · Six months extension in view of force majeure caused by covid-19 pandemic
  3. 3. 29 Jun 2021 → 31 Mar 2022
  4. 4. 31 Mar 2022 → 30 Mar 2023

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in