Nirala Greenshire Ph-1 (G6-G12,G14)
Nirala Projects Pvt Ltd
38
Project Health Score
Nirala Greenshire Ph-1 (G6-G12,G14)
High risk · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ497515/15
- Delivery vs promise UP-RERAPromised Sept 2020 · 3 extensions to Mar 2022 · deadline passed 54 months ago with no completion (OC) recorded yet0/20
- Buyer complaints on UP-RERA UP-RERA13 complaints against this project · 21 against the builder4/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ4975
- Registered on
- 31 Jul 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- NIRALA PROJECTS PRIVATE LIMITED
- Completion promised
- 30 Sept 2020
- Current deadline
- 29 Mar 2022
- Complaints on UP-RERA
- 13 · builder total 21
Deadline extensions granted (3)
- 1. 30 Sept 2020 → 29 Mar 2021 · Six months extension in view of force majeure caused by covid-19 pandemic
- 2. 29 Mar 2021 → 30 Sept 2021
- 3. 30 Sept 2021 → 29 Mar 2022
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in