HOMESNCR

Lotus Arena

Arena Superstructures Pvt Ltd

16
Project Health Score
Lotus Arena
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ5409 · flagged “Default on QPR”
    8/15
  • Delivery vs promise UP-RERA
    Promised Mar 2021 · 1 extension to Sept 2021 · deadline passed 60 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    79 complaints against this project · 84 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ5409
Registered on
11 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
ARENA SUPERSTRUCTURES PRIVATE LIMITED
Completion promised
31 Mar 2021
Current deadline
30 Sept 2021
Complaints on UP-RERA
79 · builder total 84

UP-RERA flag: Default on QPR — the builder has not filed its mandatory quarterly progress report.

Deadline extensions granted (1)
  1. 1. 31 Mar 2021 → 30 Sept 2021 · Six months extension in view of force majeure caused by covid-19 pandemic

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in