Kumar Imperial Greens

Keltech Infrastructure Limited

30
Project Health Score
Kumar Imperial Greens
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ3375
    15/15
  • Delivery vs promise UP-RERA
    Promised Jul 2020 · 4 extensions to Jun 2025 · deadline passed 15 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    46 complaints against this project · 59 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ3375
Registered on
9 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
KELTECH INFRASTRUCTURE LIMITED
Completion promised
31 Jul 2020
Current deadline
28 Jun 2025
Complaints on UP-RERA
46 · builder total 59
Deadline extensions granted (4)
  1. 1. 31 Jul 2020 → 30 Jan 2021 · Six months extension in view of force majeure caused by covid-19 pandemic
  2. 2. 31 Jul 2020 → 31 Dec 2023 · Six months extension in view of force majeure caused by covid-19 pandemic
  3. 3. 30 Jan 2021 → 31 Dec 2023
  4. 4. 31 Dec 2023 → 28 Jun 2025

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in