Hilston By Urbtech - Tower G
Golfgreen Buildcon Pvt Ltd
46
Project Health Score
Hilston By Urbtech - Tower G
High risk · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ1149815/15
- Delivery vs promise UP-RERAPromised Sept 2021 · 1 extension to Mar 2022 · deadline passed 55 months ago with no completion (OC) recorded yet0/20
- Buyer complaints on UP-RERA UP-RERA6 complaints against this project · 42 against the builder8/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ11498
- Registered on
- 15 Aug 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- GOLFGREEN BUILDCON PRIVATE LIMITED
- Completion promised
- 3 Sept 2021
- Current deadline
- 2 Mar 2022
- Complaints on UP-RERA
- 6 · builder total 42
Deadline extensions granted (1)
- 1. 3 Sept 2021 → 2 Mar 2022 · Six months extension in view of force majeure caused by covid-19 pandemic
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in