GH-07/75 Golf City

Aims Max Gardenia Developers Pvt Ltd

32
Project Health Score
GH-07/75 Golf City
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ7234 · flagged “Default on QPR”
    8/15
  • Delivery vs promise UP-RERA
    Promised Jul 2020 · 1 extension to Jan 2021 · deadline passed 68 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    8 complaints against this project · 63 against the builder
    8/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ7234
Registered on
14 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
AIMS MAX GARDENIA DEVELOPERS PRIVATE LIMITED
Completion promised
31 Jul 2020
Current deadline
30 Jan 2021
Complaints on UP-RERA
8 · builder total 63

UP-RERA flag: Default on QPR — the builder has not filed its mandatory quarterly progress report.

Deadline extensions granted (1)
  1. 1. 31 Jul 2020 → 30 Jan 2021 · Six months extension in view of force majeure caused by covid-19 pandemic

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in

Builder or buyer? Something here out of date or wrong — request a correction

We show UP-RERA's public records as they are. If UP-RERA has since updated them (for example, an order was set aside or an extension granted), tell us and share the document — we re-check with UP-RERA and update this page, usually within 2 working days.

We use your details only to respond to this request. See our privacy policy.

No flats listed in GH-07/75 Golf City right now.

Own a flat here? List it free — buyers searching this society will see it first.

Post your flat