Capital Athena (Phase-1)

Capital Infratechomes Pvt Ltd

30
Project Health Score
Capital Athena (Phase-1)
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ6310
    15/15
  • Delivery vs promise UP-RERA
    Promised Jun 2020 · 3 extensions to Sept 2022 · deadline passed 48 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    99 complaints against this project · 168 against the builder
    0/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ6310
Registered on
12 Aug 2017
Type
Residential · Ongoing
Promoter (builder company)
CAPITAL INFRATECHOMES PRIVATE LIMITED
Completion promised
30 Jun 2020
Current deadline
28 Sept 2022
Complaints on UP-RERA
99 · builder total 168
Deadline extensions granted (3)
  1. 1. 30 Jun 2020 → 29 Dec 2020 · Six months extension in view of force majeure caused by covid-19 pandemic
  2. 2. 29 Dec 2020 → 29 Dec 2021
  3. 3. 29 Dec 2021 → 28 Sept 2022

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in