Antriksh Golf City ( Phase V)
Contend Infrastructure Pvt Ltd
40
Project Health Score
Antriksh Golf City ( Phase V)
High risk · based on 3 of 6 checks
- RERA registration UP-RERARegistered UPRERAPRJ6994 · flagged “Default on QPR”8/15
- Delivery vs promise UP-RERAPromised Jul 2023 · 1 extension to Jan 2024 · deadline passed 32 months ago with no completion (OC) recorded yet0/20
- Buyer complaints on UP-RERA UP-RERA2 complaints against this project · 20 against the builder12/15
- Construction Our teamNot yet verified—
- Occupancy Certificate (OC) Our teamNot yet verified—
- Registry Our teamNot yet verified—
Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page
Official UP-RERA record
- Registration no.
- UPRERAPRJ6994
- Registered on
- 1 Aug 2017
- Type
- Residential · Ongoing
- Promoter (builder company)
- CONTEND INFRASTRUCTURE PRIVATE LIMITED ( ANTRIKSH
- Completion promised
- 31 Jul 2023
- Current deadline
- 30 Jan 2024
- Complaints on UP-RERA
- 2 · builder total 20
UP-RERA flag: Default on QPR — the builder has not filed its mandatory quarterly progress report.
Deadline extensions granted (1)
- 1. 31 Jul 2023 → 30 Jan 2024 · Six months extension in view of force majeure caused by covid-19 pandemic
Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in
Loading map…
No flats listed in Antriksh Golf City ( Phase V) right now.