Aastha Greens

Aastha Infracity Limited

38
Project Health Score
Aastha Greens
High risk · based on 3 of 6 checks
  • RERA registration UP-RERA
    Registered UPRERAPRJ1050
    15/15
  • Delivery vs promise UP-RERA
    Promised Jun 2019 · 3 extensions to Dec 2020 · deadline passed 69 months ago with no completion (OC) recorded yet
    0/20
  • Buyer complaints on UP-RERA UP-RERA
    22 complaints against this project · 32 against the builder
    4/15
  • Construction Our team
    Not yet verified
    —
  • Occupancy Certificate (OC) Our team
    Not yet verified
    —
  • Registry Our team
    Not yet verified
    —

Official data from UP-RERA, synced 11/10/2026. OC, registry and construction are checked by our team. Always verify before paying. Official UP-RERA page

Official UP-RERA record

Registration no.
UPRERAPRJ1050
Registered on
27 Jul 2017
Type
Residential · New
Promoter (builder company)
AASTHA INFRACITY LIMITED
Completion promised
30 Jun 2019
Current deadline
27 Dec 2020
Complaints on UP-RERA
22 · builder total 32
Deadline extensions granted (3)
  1. 1. 30 Jun 2019 → 29 Dec 2019
  2. 2. 29 Dec 2019 → 28 Jun 2020
  3. 3. 28 Jun 2020 → 27 Dec 2020 · Six months extension in view of force majeure caused by covid-19 pandemic

Source: Uttar Pradesh Real Estate Regulatory Authority, synced 11/10/2026. Verify at up-rera.in