Uttam Steels & Associates Consortium) Throug
Track record in Noida, Greater Noida & Yamuna Expressway, from official UP-RERA records
Projects on UP-RERA
7
0 in the current list
Flats registered
—
not filed yet
Buyer complaints on UP-RERA
Some complaints
130 complaints
Completion date extended
6 of 7
projects (registered extensions)
UP-RERA status lists
- 7 projects in abeyance. Key documents such as land records or maps were not filed with UP-RERA.
Projects (7)
| Project | Flats | Registered | Completion (promised → latest) | Complaints | Status |
|---|---|---|---|---|---|
| AASTHA UDAY UPRERAPRJ9841 | — | — | Jul 2023 → Jan 2024 (+6 mo) | Few complaints | In abeyanceUP-RERA |
| BUILTUPS ZONE II UPRERAPRJ5838 | — | — | Dec 2022 → Jun 2023 (+6 mo) | Few complaints | In abeyanceUP-RERA |
| FAIRWAY ZONE-1 UPRERAPRJ3983 | — | — | Dec 2021 → Jun 2022 (+6 mo) | Few complaints | In abeyanceUP-RERA |
| FAIRWAY ZONE-2 (Tower F & K) UPRERAPRJ4526 | — | — | Dec 2020 → Jun 2021 (+6 mo) | Some complaints | In abeyanceUP-RERA |
| FAIRWAY ZONE-4 (Tower A, G, H, J & I) UPRERAPRJ4863 | — | — | Dec 2022 → Jun 2023 (+6 mo) | Some complaints | In abeyanceUP-RERA |
| FAIRWAY ZONE-5 (TOWER C&D) UPRERAPRJ5677 | — | — | Mar 2018 | Some complaints | In abeyanceUP-RERA |
| Sushant Square UPRERAPRJ6346 | — | — | Mar 2022 → Sept 2022 (+6 mo) | Some complaints | In abeyanceUP-RERA |
Registered as: Uttam Steels & Associates Consortium) Throug
Source: UP-RERA public records for Gautam Buddh Nagar, refreshed nightly. Completion dates are as registered with UP-RERA; an extension is a registered change, not proof of a delay on site. Complaint counts are as recorded by UP-RERA and are not a judgement on the builder. Builder or buyer and something looks wrong? Tell us.