Max-Digi Infotech Private Limited

Track record in Noida, Greater Noida & Yamuna Expressway, from official UP-RERA records

WhatsApp
Projects on UP-RERA
5
all in the current list
Flats registered
—
not filed yet
Buyer complaints on UP-RERA
Some complaints
182 complaints
Completion date extended
4 of 5
projects (registered extensions)

Projects (5)

ProjectFlatsRegisteredCompletion (promised → latest)ComplaintsStatus
CYBERTHUM PHASE II
Commercial · UPRERAPRJ452606
—Sept 2021Sept 2024 Some complaintsRegisteredUP-RERA
CYBERTHUM PHASE A
Commercial · UPRERAPRJ236478
—Feb 2019Dec 2022 → Feb 2025 (+27 mo) Some complaintsRegisteredUP-RERA
CYBERTHUM PHASE B
Commercial · UPRERAPRJ240015
—Feb 2019Dec 2022 → Feb 2025 (+27 mo) Some complaintsRegisteredUP-RERA
CYBERTHUM PHASE E (BLOCK A)
Commercial · UPRERAPRJ190938
—Feb 2019Dec 2022 → Feb 2025 (+27 mo) Some complaintsRegisteredUP-RERA
CYBERTHUM PHASE H (BLOCK D)
Commercial · UPRERAPRJ674006
—Feb 2019Dec 2022 → Feb 2025 (+27 mo) Some complaintsRegisteredUP-RERA

Registered as: Max-Digi Infotech Private Limited

Source: UP-RERA public records for Gautam Buddh Nagar, refreshed nightly. Completion dates are as registered with UP-RERA; an extension is a registered change, not proof of a delay on site. Complaint counts are as recorded by UP-RERA and are not a judgement on the builder. Builder or buyer and something looks wrong? Tell us.