Intellicity Business Park Private Limited

Track record in Noida, Greater Noida & Yamuna Expressway, from official UP-RERA records

WhatsApp
Projects on UP-RERA
4
0 in the current list
Flats registered
74
as filed by the builder
Buyer complaints on UP-RERA
More complaints than usual
92 complaints · ≈23 per 100 flats
Completion date extended
2 of 4
projects (registered extensions)

UP-RERA status lists

  • 4 projects on UP-RERA's NCLT list. The builder company is in insolvency proceedings for these projects.

Projects (4)

ProjectFlatsRegisteredCompletion (promised → latest)ComplaintsStatus
INTELLICITY @PHASE 4 (OCCI & CEREBRUM)
Techzone 4 · Residential · UPRERAPRJ11522
—Aug 2017Dec 2022 → Jun 2023 (+6 mo) Very few complaintsOn UP-RERA's NCLT listUP-RERA
INTELLICITY @PHASE-3 SPINE (TOWER-A & B)
Sector 83 · Residential · UPRERAPRJ11493
—Aug 2017Dec 2021 → Jun 2022 (+6 mo) Some complaintsOn UP-RERA's NCLT listUP-RERA
INTELLICITY@PHASE-1
Sector 83 · Residential · UPRERAPRJ11448
74Aug 2017Dec 2019 More complaints than usualOn UP-RERA's NCLT listUP-RERA
INTELLICITY@PHASE-2
Commercial · UPRERAPRJ11473
—Aug 2017Dec 2019 Few complaintsOn UP-RERA's NCLT listUP-RERA

Registered as: Intellicity Business Park Private Limited

Source: UP-RERA public records for Gautam Buddh Nagar, refreshed nightly. Completion dates are as registered with UP-RERA; an extension is a registered change, not proof of a delay on site. Complaint counts are as recorded by UP-RERA and are not a judgement on the builder. Builder or buyer and something looks wrong? Tell us.