Iitl-Nimbus The Express Park View
Track record in Noida, Greater Noida & Yamuna Expressway, from official UP-RERA records
Projects on UP-RERA
5
all in the current list
Flats registered
705
as filed by the builder
Buyer complaints on UP-RERA
Few complaints
23 complaints · ≈2 per 100 flats
Completion date extended
3 of 5
projects (registered extensions)
Projects (5)
| Project | Flats | Registered | Completion (promised → latest) | Complaints | Status |
|---|---|---|---|---|---|
| THE EXPRESS PARK VIEW II- LOW RISE APARTMENTS Chi 5 · Residential · UPRERAPRJ555694 | 310 | Mar 2021 | Jan 2024 → Jan 2025 (+12 mo) | Few complaints | RegisteredUP-RERA |
| THE PARK STREET Commercial · UPRERAPRJ180127 | — | Oct 2019 | Mar 2021 → Sept 2021 (+6 mo) | No complaints | RegisteredUP-RERA |
| IITL NIMBUS THE EXPRESS PARK VIEW (TOWER I1, J1, K1) Chi 5 · Residential · UPRERAPRJ10246 | 395 | Aug 2017 | Mar 2019 → Sept 2020 (+18 mo) | Few complaints | RegisteredUP-RERA |
| IITL NIMBUS THE EXPRESS PARK VIEW (TOWER L,L1,M,M1 Chi 5 · Residential · UPRERAPRJ10096 | — | Aug 2017 | Dec 2018 | Very few complaints | RegisteredUP-RERA |
| IITL-NIMBUS THE EXPRESS PARK VIEW (TOWER I,J & K) Chi 5 · Residential · UPRERAPRJ9947 | — | Aug 2017 | Dec 2017 | Few complaints | RegisteredUP-RERA |
Registered as: Iitl-Nimbus The Express Park View
Source: UP-RERA public records for Gautam Buddh Nagar, refreshed nightly. Completion dates are as registered with UP-RERA; an extension is a registered change, not proof of a delay on site. Complaint counts are as recorded by UP-RERA and are not a judgement on the builder. Builder or buyer and something looks wrong? Tell us.