AIMS Golf Town Developers Private Limited

Track record in Noida, Greater Noida & Yamuna Expressway, from official UP-RERA records

WhatsApp
Projects on UP-RERA
4
3 in the current list
Flats registered
476
as filed by the builder
Buyer complaints on UP-RERA
More complaints than usual
142 complaints · ≈19 per 100 flats
Completion date extended
2 of 4
projects (registered extensions)

UP-RERA status lists

  • 1 project in abeyance. Key documents such as land records or maps were not filed with UP-RERA.

Projects (4)

ProjectFlatsRegisteredCompletion (promised → latest)ComplaintsStatus
AIMS GREEN AENUE (PHASE-3)
Gaur City 2 · Residential · UPRERAPRJ7262
—Aug 2017Dec 2019 → Dec 2020 (+12 mo) Some complaintsRegisteredUP-RERA
AIMS GREEN AVENUE (PHASE-1)
Gaur City 2 · Residential · UPRERAPRJ7473
476Aug 2017Dec 2018 More complaints than usualRegisteredUP-RERA
AIMS GREEN AVENUE (PHASE-2)
Gaur City 2 · Residential · UPRERAPRJ7136
—Aug 2017Jun 2019 → Dec 2020 (+18 mo) Some complaintsRegisteredUP-RERA
Aims Windsor street
UPRERAPRJ10867
——Oct 2021 Very few complaintsIn abeyanceUP-RERA

Registered as: AIMS Golf Town Developers Private Limited

Source: UP-RERA public records for Gautam Buddh Nagar, refreshed nightly. Completion dates are as registered with UP-RERA; an extension is a registered change, not proof of a delay on site. Complaint counts are as recorded by UP-RERA and are not a judgement on the builder. Builder or buyer and something looks wrong? Tell us.