AIMS Golf Town Developers Private Limited
Track record in Noida, Greater Noida & Yamuna Expressway, from official UP-RERA records
Projects on UP-RERA
4
3 in the current list
Flats registered
476
as filed by the builder
Buyer complaints on UP-RERA
More complaints than usual
142 complaints · ≈19 per 100 flats
Completion date extended
2 of 4
projects (registered extensions)
UP-RERA status lists
- 1 project in abeyance. Key documents such as land records or maps were not filed with UP-RERA.
Projects (4)
| Project | Flats | Registered | Completion (promised → latest) | Complaints | Status |
|---|---|---|---|---|---|
| AIMS GREEN AENUE (PHASE-3) Gaur City 2 · Residential · UPRERAPRJ7262 | — | Aug 2017 | Dec 2019 → Dec 2020 (+12 mo) | Some complaints | RegisteredUP-RERA |
| AIMS GREEN AVENUE (PHASE-1) Gaur City 2 · Residential · UPRERAPRJ7473 | 476 | Aug 2017 | Dec 2018 | More complaints than usual | RegisteredUP-RERA |
| AIMS GREEN AVENUE (PHASE-2) Gaur City 2 · Residential · UPRERAPRJ7136 | — | Aug 2017 | Jun 2019 → Dec 2020 (+18 mo) | Some complaints | RegisteredUP-RERA |
| Aims Windsor street UPRERAPRJ10867 | — | — | Oct 2021 | Very few complaints | In abeyanceUP-RERA |
Registered as: AIMS Golf Town Developers Private Limited
Source: UP-RERA public records for Gautam Buddh Nagar, refreshed nightly. Completion dates are as registered with UP-RERA; an extension is a registered change, not proof of a delay on site. Complaint counts are as recorded by UP-RERA and are not a judgement on the builder. Builder or buyer and something looks wrong? Tell us.